We are proud to announce that the Fenili plant has been successfully started up following a significant modification. The key upgrades included:
* Replacement of the flat table with a Crescent Former, enhancing performance and product quality.
* Complete renewal of the low-voltage system to enhance efficiency, reliability, and compliance with safety standards.
* Replacement of the entire DCS system, for more advanced and precise plant control.
A great achievement made possible by the dedication and expertise of our team!
Photo: EIL /REPLUS